Development Timeline

June 2018

The National Lottery Heritage Fund Award Granted

December 2018

We closed our doors to begin redevelopment work

23rd September 2019

Building construction work began

Brims Construction won the contract to refurbish the building after a careful tender process.

Brims Construction won the contract to refurbish the building after a careful tender process.

July 2021

The Common Room opened it's doors

The building officially opened its doors in July 2021; slightly delayed due to the Covid-19 pandemic.

The building officially opened its doors in July 2021; slightly delayed due to the Covid-19 pandemic.